HomeMy WebLinkAbout20240208124152704 City Hall Roof Rehabilitation DocumentsDEPARTMENT OF PUBLIC WORKS CITY OF DIAMOND BAR CALIFORNIA CONTRACT DOCUMENTS FOR CITY HALL RE-ROOF/REHABILITATION PROJECT All Questions Regarding This Project Are to be Submitted in Planet Bids All Bid Documents Are to be Submitted in Planet Bids Mr. Jason Williams Maintenance Supervisor City of Diamond Bar (909) 839-7059 Jwilliams@DiamondBarCA.Gov November 17, 2023 BIDDER'S EXAMINATION OF SITE: Each bidder shall examine carefully the site of the proposed work and the contract documents therefore. It will be assumed that the bidder has investigated and is satisfied as to the conditions to be encountered as to the character, quality, and quantity of materials to be furnished, and as to the requirements of the contract, specifications and drawings. The name of the individual who examined the site of the work and the date of such examination shall be stated in the proposal. By submitting a bid, the bidder will be held to have personally examined the site and the drawings, to have carefully read the specifications, and to have satisfied himself as to his ability to meet all the difficulties attending the execution of the proposed contract before the delivery of his proposal, and agrees that if he is awarded the contract, he will make no claim against the City of Diamond Bar based on ignorance or misunderstanding of the contract provisions. Also, per Public Contract Code section 3400(c) (2) the specified replacement roofing material type and manufacturer is required “in order to match other products in use” on the particular project or improvement. INSURANCE:Contractor shall not commence work under this Agreement until it has obtained all insurance required hereunder in a company or companies acceptable to City nor shall the Contractor allow any sub-contractor to commence work on his sub-contract until all insurance required of the sub-contractor has been obtained. The Contractor shall take out and maintain at all times during the life of this contract the following policies of insurance: a. Workers' Compensation Insurance: Before beginning work, the Contractor shall furnish to the City a certificate of insurance as proof that he has taken out full workers' compensation insurance for all persons whom he may employ directly or through sub-contractors in carrying out the work specified herein, in accordance with the laws of the State of California. Such insurance shall be maintained in full force and effect during the period covered by this contract. In accordance with the provisions of Section 3700 of the California Labor Code, every Contractor shall secure the payment of compensation to his employees. The Contractor, prior to commencing work, shall sign and file with the City a certification as follows: "I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability for workers' compensation or to undertake self- insurance in accordance with the provisions of that Code, and I will comply with such provisions before commencing the performance of work of this contract." b. For all operations of the Contractor or any sub- contractor in performing the work provided for herein, insurance with the following minimum limits and coverage: 1) General Liability - $1,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this Agreement or the general aggregate limit shall be twice the required occurrence limit. 2) Automobile - $1,000,000 per accident for bodily injury and property damage. c. Each such policy of insurance provided for in paragraph b. shall: 1) Be issued by an insurance company approved in writing by City, which is authorized to do business in the State of California. 2) Name as additional insured the City of Diamond Bar, its officers, agents and employees, and any other parties specified in the bid documents to be so included; 3) Specify it acts as primary insurance and that no insurance held or owned by the designated additional insured shall be called upon to cover a loss under the policy; 4) Contain a clause substantially in the following words: "It is hereby understood and agreed that this policy may not be canceled nor the amount of the coverage thereof reduced until thirty (30) days after receipt by City of a written notice of such cancellation or reduction of coverage." 5) Waives all right of subrogation against all persons and entities specified in subparagraph 4.c.(2) hereof to be listed as additional insured in the policy of insurance provided for in paragraph b. by reason of any claim arising out of or connected with the operations of Contractor or any sub-contractor in performing the work provided for herein; 6) Otherwise be in form satisfactory to the City. d. The Contractor shall, prior to performing any work under this Agreement, deliver to the City Manager or his designee the original policies of insurance required in paragraphs a. and b. hereof, or deliver to the City Manager or his designee a certificate of the insurance company, showing the issuance of such insurance, and the additional insured and other provisions required herein. PREVAILING WAGE: Notice is hereby given that in accordance with the provisions of California Labor Code, Division 2, Part 7, Chapter 1, Articles 1 and 2, the Contractor is required to pay not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the public works is performed, and not less than the general prevailing rate of per diem wages for holiday and overtime work. In that regard, the Director of the Department of Industrial Relations of the State of California is required to and has determined such general prevailing rates of per diem wages. Copies of such prevailing rates of per diem wages are on file in the Office of the City Clerk of the City of Diamond Bar, 21810 Copley Drive, Diamond Bar, California, and are available to any interested party on request. City also shall cause a copy of such determinations to be posted at the job site. Contractor shall forfeit, as penalty to City, not more than two hundred dollars ($200.00) for each laborer, workman or mechanic employed for each calendar day or portion thereof, if such laborer, workman or mechanic is paid less than the general prevailing rate of wages hereinbefore stipulated for any work done under this Agreement, by him or by any sub-contractor under him. Contractor and any of its sub-contractors must be registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5, which precludes the award of a contract for a public work on any public works project awarded after April 1, 2015 to a person not registered. This Agreement is subject to compliance monitoring and enforcement by the Department of Industrial Relations. INTERPRETATION OF DOCUMENTS: If any person contemplating submitting a bid for proposed contract is in doubt as to the true meaning of any part of the drawings, specifications, or other contract documents, or finds discrepancies in, or omissions from the drawings and specifications, he may submit to the City a written request for an interpretation or correction thereof. The person submitting the request will be responsible for its prompt delivery. Any interpretation or correction of the contract documents will be made only by Addendum duly issued and a copy of such addendum will be mailed or delivered to each person receiving a set of the contract document. No person is authorized to make any oral interpretation of any provision in the contract documents to any bidder, and no bidder is authorized to rely on any such unauthorized oral interpretation. DISQUALIFICATION OF BIDDERS: More than one proposal from an individual, firm partnership, corporation, or association under the same or different names, will not be considered. Reasonable grounds for believing that any bidder is interested in more than one proposal for the work contemplated will cause the rejection of all proposals in which such bidder is interested. If there is reason for believing that collusion exists among the bidders, all bids will be rejected and none of the participants in such collusion will be considered in future proposals. No award will be made to any bidder who cannot give satisfactory assurance as to his ability to carry out the Contract, both from his financial rating and by reason of his previous experience as a Contractor on work of the nature contemplated in the Contract. The bidder may be required to submit his record of work of similar nature to that proposed under these specifications, and unfamiliarity with the type of work may be sufficient cause for rejection of the bid. INELIGIBLE SUBCONTRACTORS: The successful bidder shall be prohibited from performing work on this project with a subcontractor who is ineligible to perform work on the project pursuant to Section 1777.1 or 1777.7 of the Labor Code. AWARD OF CONTRACT: No proposal will be considered from a Contractor who is not licensed as a Class C-39 contractor at time of award in accordance with the provisions of the Contractor’s License Law (California Business and Professions Code, Section 7000 et seq.) and rules and regulations adopted pursuant thereto or to whom a proposal form has not been issued by the City of Diamond Bar. The City may award the Contract to the lowest responsible bidder on the total base bid. Bids will be compared on the basis of the lowest possible cost relative to the alternate or alternates selected and the Contract, if awarded, will be awarded to a responsible bidder whose proposal complies with the requirements of these specifications. The award, if made, will be made within ninety (90) calendar days after the opening of the proposals; provided that the award may be made after said period of the successful bidder shall not have given the City written notice of the withdrawal of his bid. A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Public Contract Code §4104, or engage in the performance of any contract for public work, as defined in the Public Contract Code, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of Labor Code §1771.1 for an unregistered contractor to submit a bid that is authorized by Business and Professions Code § 7029.1 or by Public Contract Code §§ 10164 and 20103.5, provided the contractor is registered to perform public work pursuant to Labor Code § 1725.5 at the time the contract is awarded. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. The prime contractor is required to post job sits as prescribed by regulation pursuant to Labor Code § 1771.4 and all contractors must secure the payment of compensation to its employees pursuant to Labor Code § 1869. COMPETENCY OF BIDDERS: In selecting the lowest responsible bidder, consideration will be given not only to the financial standing but also to the general competency of the bidder including qualifications, references, proper licensing, adequate workforce and experience for the performance of the work covered by the proposal. QUALIFICATION OF BIDDERS: Each bidder shall be skilled and regularly engaged in the general class or type of work called for under the contract. A statement setting forth his/her experience shall be submitted by each bidder on the EXPERIENCE STATEMENT form provided. EXPERIENCE STATEMENT To be responsive, the bidder must list below a minimum of three public agencies for which bidder has performed similar work within the past five years. Only projects in excess of $200,000 each qualify as similar for this project. 1. Project Title Contract Amount Type of Work Client Agency Project Manager Phone Date Completed % Subcontracted 2. Project Title Contract Amount Type of Work Client Agency Project Manager Phone Date Completed % Subcontracted 3. Project Title Contract Amount Type of Work Client Agency Project Manager Phone Date Completed % Subcontracted NOTE: If requested by the City, the bidder shall furnish a certified financial statement, references, and other information sufficiently comprehensive to permit an appraisal of his current financial condition. Bidder's Signature Each bidder shall possess a valid Contractor's License issued by the Contractor's State License Board at the time his/her bid is submitted. The class of license shall be applicable to the work specified in the contract. Each bidder shall also have no less than five (5) years of experience in the magnitude and character of the work bid. Bidder Qualifications called for to be submitted at time of bid include, but are not necessarily limited to: 1. The Contractor shall have been in business under the same name and California Contractors License for a minimum of five (5) continuous years prior to the bid opening date for this Project. The license used to satisfy this requirement shall be of same type required by the contract. 2. License classification shall be as required by the contract specifications. 3. The Contractor shall have five (5) years of experience in the Application of fluid-applied roof membrane. 4. The Contractor shall perform at least 50% of contract with its own forces. EXECUTION OF CONTRACT: The bidder to whom award is made shall execute a written contract with the City on the agreement form provided, and shall secure all insurance and bonds as herein provided within ten (10) days from the date of written notice of the award. Failure or refusal to enter into a contract as herein provided, or to conform to any of the stipulated requirements in connection therewith shall be just cause for the annulment of the award and the forfeiture of the proposal guarantee. If the successful bidder refuses or fails to execute the Contract, the City may award the Contract to the next lowest responsible bidder or re-advertise. On the failure or refusal of the lowest responsible bidder or next lowest responsible bidder to execute the Contract, such bidder's guarantees shall be likewise forfeited to the City. PERMITS, FEES AND LICENSES: The Contractor shall possess a valid business license prior to the issuance of the first payment made under this Contract. CLAIMS FILING AND PROCESSING: The City and Bidder agree to attempt to orally resolve any disputes which may give rise to a claim (hereafter, "Claim") that falls within the definition of Public Contract Code section 9204 (hereafter, "Section 9204"). If these efforts are unsuccessful, the City and Bidder shall process the Claim in accordance with Section 9204. In summary, if the Bidder decides to submit a Claim to the City, it shall be sent by registered or certified mail, return receipt requested, together with reasonable documentation to support the Claim. A Claim may include a Claim by a subcontractor or a lower tier subcontractor meeting the requirements of Section 9204(d)(5). Within 45 days of receipt of the Claim, or any extension thereof agreed upon by the City and the Bidder, the City will conduct a reasonable review of the Claim and provide the Bidder with a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Payment of any undisputed portion of the Claim shall be made within 60 days after the City issues its written statement. If the City does not provide a written statement within the time specified, the Claim shall be deemed rejected. If the Bidder disputes the City's written statement or if the Claim is deemed rejected, the Bidder may demand in writing by registered or certified mail to the City, return receipt requested, an informal conference to meet and confer in an effort to settle the disputed portion of any Claim. Within 30 days of receipt of such written demand, the City shall schedule a meet and confer conference. If any portion of the Claim remains in dispute after the conference, the City shall, within 10 City business days of the conclusion of the conference, provide the Bidder with a written statement identifying any portion that remains in dispute and any portion that is undisputed. Payment of any undisputed portion shall be made within 60 days after the City issues its written statement. Any remaining disputed portion shall be submitted to nonbinding mediation in accordance with Section 9204(c)(2)(B), unless the Bidder and City waive the mediation upon mutual written agreement. CONFLICT OF INTEREST: In the procurement of supplies, equipment, construction and services by sub- recipients, the conflict-of-interest provisions in (State LCA-24 CFR 85.36 and Non-Profit Organizations – 24 CFR 84.4), OMB Circular A-110, and 24 CFR 570.611, respectively, shall apply. No employee, officer or agent of the sub-recipient shall participate in selection or in award of administration of a contract supported by Federal funds if a conflict of interest, real or apparent, would be involved. DECLARATION OF ELIGIBILITY TO CONTRACT [Labor Code Section 1777.1; Public Contract Code Section 6109] The undersigned, a duly authorized representative of the contractor, certifies and declares that: 1. The contractor is aware of Sections 1777.1 and 1777.7 of the California Labor Code, which prohibit a contractor or subcontractor who has been found by the Labor Commissioner or the Director of Industrial Relations to be in violation of certain provisions of the Labor Code, from bidding on, being awarded, or performing work as a subcontractor on a public works project for specified periods of time. 2. The contractor is not ineligible to bid on, be awarded or perform work as a subcontractor on a public works project by virtue of the foregoing provisions of Sections 1777.1 or 1777.7 of the California Labor Code or another provision of law. 3. The contractor is aware of California Public Contract Code Section 6109, which states: (a) A public entity, as defined in Section 1100 [of the Public Contract Code], may not permit a contractor or subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to Section 1777.1 or 1777.7 of the Labor Code to bid on, be awarded, or perform work as a subcontractor on, a public works project. Every public works project shall contain a provision prohibiting a contractor from performing work on a public works project with a subcontractor who is ineligible to perform work on the public works project pursuant to Section 1777.1 or 1777.7 of the Labor Code. (b) Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract, and any public money that may have been paid to a debarred subcontractor by a contractor on the project shall be returned to the awarding body. The contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project. 4. The contractor has investigated the eligibility of each and every subcontractor the contractor intends to use on this public works project, and determined that none of them is ineligible to perform work as a subcontractor on a public works project by virtue of the foregoing provisions of the Public Contract Code Sections 1777.1 or 1777.7 of the Labor Code, or any other provision of law. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Executed this day of ________________, 201_, at ___________________ (place of execution). Signature Name: Title: Name of Contractor: _____________________________ BIDDER'S VIOLATION OF LAW/SAFETY QUESTIONNAIRE In accordance with Government Code Section 14310.5 and in conformance with Public Contract Code Section 10162, the Bidder shall complete, under penalty of perjury, the following questionnaire: QUESTIONNAIRE Has the Bidder, any officer, principal or employee of the Bidder who has a proprietary interest in the business of the Bidder, ever been disqualified, removed, or otherwise prevented from bidding on or completing a federal, state or local government project because of violation of law or a safety regulation? YES NO If the answer is yes, explain the circumstances in the following space: STATEMENT In conformance with Public Contract Code Section 10232, the Contractor, hereby states under penalty of perjury, that no more than on final unappealable finding of contempt of court by a federal court has been issued against the Contractor within the immediately preceding two-year period because of the Contractor’s failure to comply with an order of a federal court which orders the Contractor to comply with an order of the National Labor Relations Board. NOTE: The above Statement and Questionnaire are part of the Proposal. Signing this Proposal on the signature portion thereof shall also constitute signature of this Statement and Questionnaire. Bidders are cautioned that making a false certification may subject the certifier to criminal prosecution. CONTRACTOR'S INDUSTRIAL SAFETY RECORD Project Identification Bid Date This information must include all construction work undertaken in the State of California by the bidder and any partnership, joint venture or corporation that any principal of the bidder participated in as a principal or owner for the last five calendar years and the current calendar year prior to the date of bid submittal. Separate information shall be submitted for each particular partnership, joint venture, corporation or individual bidder. The bidder may attach any additional information or explanation of data, which he would like, taken into consideration in evaluating the safety record. An explanation must be attached of the circumstances surrounding any and all fatalities. ITEM 5 CALENDAR YEARS PRIOR TO CURRENT YEAR CURRENT YEAR 2018 2019 2020 2021 2022 TOTAL 2023 No. of Contracts Total dollar amount of contracts (in 1,000’s) No. of lost workday cases No. of lost work day cases involving permanent transfer to another job or termination of employment No. of lost workdays *The information required for this item is the same as required for columns 3 to 6, Code 10, Occupational Injuries, Summary - Occupational Injuries and Illnesses, OSHA No. 102. The above information was compiled from the records that are available to me at this time and I declare under penalty of perjury that the information is true and accurate within the limitations of these records. ______________________________ ________________________________ Name of Bidder (Print Signature ______________________________ ________________________________ Address State Contractor’s Lic. No. & Class ______________________________ ________________________________ City Zip Code Telephone