HomeMy WebLinkAbout20240731 Daily Report
REPORT NO. 60
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/31/2024
Day of Week: Wednesday
Start Time: 7:00AM
Finish Time: 3:30PM
Total Hours: 8
DAILY REPORT
Page 1 of 5
Prime Contractor's Activities:
• The contractor paving crew continued constructing 2.0" AC on Gateway Center using a
paving machine.
• A sand truck sprayed sand on the rubberized asphalt to limit tracking to the city streets.
• Three steel drum rollers were used to compact AC.
• The paving crew raised (13) water valves to grade during the paving operation.
• A soil technician from GMU was at the job site to conduct AC tests. He took several tests on AC and all passed
with 95% or better.
• A Black Gold oil truck sprayed oil on all new grinding AC prior to paving and a water truck sprayed water to
minimize dust.
• A street sweeper was at the job site to clean up the streets during the paving operation
Materials Placed/Quantities Measured:
• The paving crew laid out 1434.43 tons of asphalt using mix design ARHMGG-C ½” PG 64-16.
• 13 water valves were raised to grade on Gateway Center Drive.
Sub-Contractors/Sub-Consultants Activities:
• EBS utilities adjusting, Inc. Crew of five set up traffic control on Golden springs Drive. They began adjusting
sewer and storm manholes to grade. The crew adjusted the total of 14 manholes.
Traffic Control:
• The traffic control crew placed road construction signs, cones, and arrow boards in the vicinities of the
construction project. Flagmen were provided throughout the day to help with traffic control.
Visitors:
• Christian Malpica
Notes:
•
Weather
Cool AM
Hot PM
Temperature
90 Min
62 Max
REPORT NO. 60
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/31/2024
Day of Week: Wednesday
Start Time: 7:00AM
Finish Time: 3:30PM
Total Hours: 8
DAILY REPORT
Page 2 of 5
Manpower / Equipment
(O)- Owner / Operator
(R)- Rental
(F) - Foreman
COMPANY TRADE
Onyx Construction 1 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver ID Hrs. # EQUIPMENT NAME
1 Foreman Truck O Mario Alvarado 1 B1 10 F/O
1 Skip Loader O Adam Alvarado 1 B2 8.5 O
1 Sweeper R Tonito Martinez 1 B7 8.5 O
1 TC Truck O Miguel Miramontes 1 B20 8.5 O
1 Water Truck O Ivan Alverado 1 8 O
1 Paving Machine O Alberto Urera 1 8 O
1 Mini Grinder O Guillermo Maciel 1 8 O
1 Super 10 Dump R Rodolfo Pinada 1 8 L
1 Loaded Truck O Martin Preciado 1 8 L
1 Crack Sand Truck O Elias Sanchez 1 8 L
1 Arrow Board O Pedro Gonzalez 1 8
8.5 L
3 Rollers O Jose de la Riva 1 8 L
1 Black Gold Sand O Luiis Becerra 1 8 O
1 Black Gold Oil O Mike M 1 9 L
1 Arrow Board O Fernando Adodaca 1 9 O
1
MTV Moving
transfer vehicle O 1
1
1
1
1
1
Bid Item Description Quantities 1
B-20
Construct ARAM
OVERLAY 2.0""
Depth
1434.43 tons 1
B-1 Mobilization LS 1
B-2 Traffic control LS 1
B-7 Adjust water valves
and cover to grade. 13 1
B-8 &B-9 Adjust SDMH/SMH to
grade 14 1
1
1
1
1
REPORT NO. 60
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/31/2024
Day of Week: Wednesday
Start Time: 7:00AM
Finish Time: 3:30PM
Total Hours: 8
DAILY REPORT
Page 3 of 5
(O)- Owner / Operator
(R)- Rental
(F) - Foreman Company COMPANY TRADE
EBS
UTILITIES
ADJUSTING
INC
Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver Traffic Control ID Hrs. EQUIPMENT NAME
MH Truck O Eluterio Robles B8 8
F
#6,#1022 O Eugenio Duarte B9 8 L
19ft Flatbed
Truck O Maynor 8 L
#1258 O Monterosso 8 L
Dump Truck O Gustavo Tapia 8 L
#16,#1040 O Jose Ramirez 8 L
O
O
R
R
R
R
Bid
Item Description Qtys
REPORT NO. 60
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/31/2024
Day of Week: Wednesday
Start Time: 7:00AM
Finish Time: 3:30PM
Total Hours: 8
DAILY REPORT
Page 4 of 5
Photos
REPORT NO. 60
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/31/2024
Day of Week: Wednesday
Start Time: 7:00AM
Finish Time: 3:30PM
Total Hours: 8
DAILY REPORT
Page 5 of 5
End of Report