HomeMy WebLinkAbout20240726 Daily Report
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 1 of 7
Prime Contractor’s Activities:
• ONYX paving crew laid out 2.5" of A.C on Grande Ave from Summit ridge Dr, STA 54+00
to Summit ridge Drive, STA 67+00
• Approximately 1300 LF of A.C were placed on Grand Avenue.
• The contractor used a paving machine to lay down the A.C and three rollers were at the
job site compacting the A.C.
• A soil technician was at the job site. The technician from GMI was hired by the contractor to conduct
compaction tests on the A.C.
• Black Gold oil truck sprayed oil on all grinded A.C prior to paving
• Black gold sand truck sprayed sand on all new Asphalt to minimize tracking.
Materials Placed/Quantities Measured:
• ONYX paving crew placed 1469.54 tons of A.C on Grand Avenue using mix design ARHM – GG – C ½” PG 64- 16.
Per approved plan.
• American Asphalt South, Inc. Slurry seal crew placed 185,004 square foot of Type 2 slurry seal on various
streets.
• The grinding crew grinded 145,000 square feet of A.C on Copley Dr and Gateway Center Drive.
Sub-Contractors/Sub-Consultants Activities:
• Pavement rehab grinding crew have completed the 2” grinding on Copley Dr and Gateway Center Dr using 7’
wide grinder and a mini grinder. Approximately 145,000 square feet were completed.
• A sweeper and a water truck were at the job site all day cleaning up the job site and spraying water to
minimize the dust.
• American Asphalt crew laid out Type 2 slurry seal on the following streets:
• Crooked Creek from Gold Run to cul-de-sac
• Chirping Sparrow Rd from Calmbrook Ln to Cul-de-sac.
• Calmbrook Ln from Chirping Sparrow Rd to cul-de-sac.
• Greyfield Ln from Chirping Sparrow Rd to Cul-de-sac.
• Cherrydale Dr from S Diamond Bar Blvd to Cul-de-sac.
• Sugar pine Pl from Diamond Bar Blvd to slurry limit
• S Diamond bar Blvd from Brea Canyon to slurry limit.
• Hideout Dr from Castle Rock Rd to Cul-de-sac.
• Lasso Dr from Castle Rock Rd to cul-de-sac.
• Castle Rock Rd from Cold springs to Hipass.
Traffic Control:
• The contractor placed traffic control per approved plan. They placed road construction signs, arrow boards
and cones throughout the project in the vicinity of the construction zone. The contractor provided flagmen
throughout the project as needed.
Visitors:
• Christian Malpica
Weather
Cool AM
Hot PM
Temperature
69 Min
96 Max
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 2 of 7
Manpower / Equipment
(O)- Owner / Operator
(R)- Rental
(F) - Foreman
COMPANY TRADE
Onyx Construction 1 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver ID Hrs. # EQUIPMENT NAME
1 Foreman Truck O Jose Becerra 1 A2 8 8
1 Skip Loader O Nathan Becerra 1 B19 8 8
1 Sweeper R Arron Becerra 1 B21 8 8
1 TC Truck O Brett Dare 1 8 8
1 Water Truck O Ismael Fernandez 1 8 8
1 Grinder O Vincet Fernandez 1 8 8
1 Mini Grinder O Jeremy Woolley 1 8 8
1 Supper 10 Dump R Mario Solorzano 1 8 8
20 Loaded Truck O Richard Alvarez 1 8 8
1
Crack Sand
Truck O Moses Twyman 1 8 8
1 Paving Machine O Edger Vasguez 1 8 8
3 Roller O Bryan Posas 1 8 8
1 Black Gold Sand Michael Rincon 1 8 8
1 Black Gold Oil David Gurrola 1 8 8
3 Arrow Board O Ismael Fernandez 1 8 8
Jeremy Wolley 1 8 8
Mario Alvarado 1 10.5 10.5
Adam Alvarado 1 9 9
Talno Martines 1 9 9
Miguel Mivaontes 1
Luis Bacona 1 8.5 8.5
Bid
Item Description Quantities Ivan Alverado 1 8.5 8.5
A-2 Traffic Control And
Public Safety 1 Fernando Adodaca 1 8.5 8.5
B-21 ARHM 2.5 Overlay 1469.54 tons Adam Alvarado 1 8.5 8.5
B-19 2.5 Grind Out 145,000 square feet Martin Perciado 1 9 9
Elins Sanchez 1 8.5 8.5
Jose Deln Riva 1 8.5 8.5
Jose Guence 1 8.5 8.5
Guillemo Macrel 1 9.5 9.5
Rodolfo Pinada 1 9 9
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 3 of 7
(O)- Owner / Operator
(R)- Rental
(F) - Foreman Company COMPANY TRADE
American
Asphalt South,
Inc. (Slurry)
2 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver Traffic Control ID Hrs. EQUIPMENT NAME
1 Lowboy
Loader O Donato
Franco 2 A16 9
1 Slurry Truck O Eduardo De
Santiago 2 A16 9
1 Slurry Truck O Frank Murrillo 2 A16 9
1 Slurry Truck O Luis
Arizmendi 2 A16 9
1 TC Truck O Jose Cordova 2 A16 9
1 TC Truck O Rudy Valdez 2 A16 10
1 TC Truck O George
Sanchez 2 A16 9
1 Pickup O Gilbert
Sanchez 2 A16 9
1 Pickup R Alberto
Medina 2 A16 10
1 Dump
Truck/Roller R Jeff Hunter 2 A16 10
1 Tanker R
Saw Truck R
Bid
Item Description Qtys
A-16 Application of Type ll
slurry seal
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 4 of 7
Photos
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 5 of 7
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 6 of 7
REPORT NO. 57
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/26/2024
Day of Week: Friday
Start Time: 8:00 am
Finish Time: 4:00 pm
Total Hours: 8
DAILY REPORT
Page 7 of 7
End of Report