REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 1 of 7
Prime Contractor’s Activities:
• ONYX paving crew laid out 2.5" of A.C on Grande Ave from Rolling
Knob Rd, STA 24+00
• To Country View Dr, STA 38+75
• Approximately 96,000 square feet of A.C were placed on Grand
Avenue.
• The contractor used a paving machine to lay down the A.C and three rollers were at the
job site compacting the A.C.
• A soil technician was at the job site. The technician from GMI was hired by the
contractor to conduct compaction tests on the A.C.
• Black Gold oil truck sprayed oil on all grinded A.C prior to paving
• Black gold sand truck sprayed sand on all new Asphalt to minimize tracking.
Materials Placed/Quantities Measured:
• ONYX paving crew placed 1426.57 tons of A.C on Grand Avenue using mix design ARHM
– GG – C ½” PG 64- 16. per approved plan.
• American Asphalt South, Inc. Slurry seal crew placed 212,858 square feet of Type 2
slurry seal on various streets.
Sub-Contractors/Sub-Consultants Activities:
• American Asphalt crew laid out Type 2 slurry seal on the following streets:
o E Oak Crest Dr. from Ridge Pt to Brea Canyon Cutoff.
o Crooked Creek Dr. from Mapache Dr. to Cold Springs Ln.
o Birch Hill Dr. from Evergreen Springs Dr. To Castle Rock Rd.
o Sunbright Dr. from Fountain Springs to Evergreen Springs.
o Fallow Field Dr. from Brea Canyon Cutoff to E Malad Ct.
o Canyon Ridge Rd. From Peaceful Hills Rd. To Eagle Crest.
Traffic Control:
• The contractor placed traffic control per approved plan. They placed road construction
signs, arrow boards and cones throughout the project in the vicinity of the construction
zone. The contractor provided flagmen throughout the project as needed.
Visitors:
• Christian Malpica
Notes:
• No grinding operations were observed on Wednesday July 22nd.
Weather
Cool AM
Hot PM
Temperature
69 Min
96 Max
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 2 of 7
Manpower / Equipment
(O)- Owner / Operator
(R)- Rental
(F) - Foreman
COMPANY TRADE
Onyx Construction 1 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver ID Hrs. # EQUIPMENT NAME
1 Foreman Truck O Jose Becerra 1 A2 0
1 Skip Loader O Nathan Becerra 1 B19 0
1 Sweeper R Arron Becerra 1 0
1 TC Truck O Brett Dare 1 0
1 Water Truck O Ismael Fernandez 1 0
1 Grinder O Vincet Fernandez 1 0
1 Mini Grinder O Jeremy Woolley 1 0
1 Supper 10 Dump R Mario Solorzano 1 0
20 Loaded Truck O Richard Alvarez 1 0
1 Crack Sand Truck O Moses Twyman 1 0
1 Paving Machine O Edger Vasguez 1 8 8
3 Roller O Bryan Posas 1 8 8
1 Black Gold Sand Michael Rincon 1 8 8
1 Black Gold Oil David Gurrola 1 8 8
3 Arrow Board O Ismael Fernandez 1 8 8
Jeremy Wolley 1 8 8
Mario Alvarado 1 10 10
Adam Alvarado 1 9 9
Talno Martines 1 9 9
Miguel Mivaontes 1 9 9
Luis Bacona 1 8.5 8.5
Bid Item Description Quantities Ivan Alverado 1 8.5 8.5
A-2 Traffic Control And
Public Safety 1 Fernando Adodaca 1 8.5 8.5
B-21 ARHM 2.5 Overlay 1426.57 tons Joseph Caenez 1 9.5 9.5
Martin Perciado 1 9 9
Elins Sanchez 1 8.5 8.5
Jose Deln Riva 1 8.5 8.5
Jose Guence 1 8.5 8.5
Guillemo Macrel 1 9.5 9.5
Rodolfo Pinada 1 9.5 9.5
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 3 of 7
(O)- Owner / Operator
(R)- Rental
(F) - Foreman Company COMPANY TRADE
American
Asphalt South,
Inc. (Slurry)
2 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver Traffic Control ID Hrs. EQUIPMENT NAME
1 Lowboy
Loader O Donato
Franco 2 A16 9
1 Slurry Truck O Eduardo De
Santiago 2 A16 9
1 Slurry Truck O Frank Murrillo 2 A16 9
1 Slurry Truck O Luis
Arizmendi 2 A16 9
1 TC Truck O Jose Cordova 2 A16 9
1 TC Truck O Rudy Valdez 2 A16 10
1 TC Truck O George
Sanchez 2 A16 9
1 Pickup O Gilbert
Sanchez 2 A16 9
1 Pickup R Alberto
Medina 2 A16 10
1 Dump
Truck/Roller R Jeff Hunter 2 A16 10
1 Tanker R
Saw Truck R
Bid
Item Description Qtys
A-16 Application of Type ll
slurry seal 212,858 square feet
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 4 of 7
Photos
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 5 of 7
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 6 of 7
REPORT NO. 55
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/24/2024
Day of Week: Wednesday
Start Time: 8:00 am
Finish Time: 3:30 pm
Total Hours: 8
DAILY REPORT
Page 7 of 7
Work in progress
End of Report