HomeMy WebLinkAbout20240723 Daily Report
REPORT NO. 54
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/23/2024
Day of Week: Tuesday
Start Time: 7:00
Finish Time: 5:00
Total Hours: 9.5
DAILY REPORT
Page 1 of 5
Prime Contractor’s Activities
• ONYX paving crew laid out 2.5" of A.C on Grande Ave from STA 10+00 to STA 24+00.
• Approximately 1400 LF of A.C were placed.
• The contractor used a paving machine to lay down the A.C and three rollers were at the
job site compacting the A.C.
• I met a soil technician at the job site. The technician from GMI was hired by the contractor to conduct
compaction tests on the A.C.
• Black Gold oil Truck sprayed oil on all grinded A.C prior to paving
• Black gold sand Truck sprayed sand on all new Asphalt to minimize tracking.
Materials Placed/Quantities Measured:
• ONYX paving crew placed 1556.26 tons of A.C on Grand Avenue using mix design ARHM – GG – C ½” PG 64- 16.
Per approved plan.
• American Asphalt South, Inc. Slurry seal crew placed 170485 square feet of Type 2 slurry seal on various streets
and placed 66000 Sq. ft. over chip seal.
• American Asphalt rehab total square footage of removal was 136,327 square feet.
Sub-Contractors/Sub-Consultants Activities:
• Pavement rehab grinding crew grinded 2.5" of A.C on Grand Avenue using 7’ wide grinder between STA 51+00
and STA 75+25. Approximately 2425 LF were completed.
• A sweeper was at the job site all day cleaning up the job site and a water Truck was at the job site spraying the
grinded street to minimize the dust.
• American Asphalt crew laid out Type 2 slurry seal on the following streets.
• E Oak. Crest Dr from Ridge point Dr. To Brea Canyon cutoff.
• Crooked Creek Dr From. Apache Dr. To Cold Spring Ln
• Birch Hill Dr from Evergreen springs Dr. to Castle Rock Rd.
• Sunbright Dr from Fountain Springs to Evergreen Springs
• Fallow field Dr from Brea Canyon to E Malad Ct
• Canyon Ridge Rd from Peaceful hills Rd to Eaglecrest.
Traffic Control:
• The contractor placed traffic control per approved plan. They placed road construction signs and cones through
out the project in the vicinity of the construction zone. The contractor provided flagmen throughout the
project as needed.
Visitors:
• Christian Malpica
Notes:
•
Weather
Cool AM
Hot PM
Temperature
68 Min
94 Max
REPORT NO. 54
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/23/2024
Day of Week: Tuesday
Start Time: 7:00
Finish Time: 5:00
Total Hours: 9.5
DAILY REPORT
Page 2 of 5
Manpower / Equipment
(O)- Owner / Operator
(R)- Rental
(F) - Foreman
COMPANY TRADE
Onyx Construction 1 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver ID Hrs. # EQUIPMENT NAME
1 Foreman Truck O Jose Becerra 1 A2 11.5 11.5
1 Skip Loader O Nathan Becerra 1 B19 11.5 11.5
1 Sweeper R Arron Becerra 1 B21 11.5 11.5
1 TC Truck O Brett Dare 1 11.5 11.5
1 Water Truck O Ismael Fernandez 1 11.5 11.5
1 Grinder O Vincet Fernandez 1 11.5 11.5
1 Mini Grinder O Jeremy Woolley 1 11.5 11.5
1 Supper 10 Dump R Mario Solorzano 1 11.5 11.5
20 Loaded Truck O Richard Alvarez 1 11.5 11.5
1
Crack Sand
Truck O Moses Twyman 1 0
1 Paving Machine O Edger Vasguez 1 8 8
3 Roller O Bryan Posas 1 8 8
1 Black Gold Sand Michael Rincon 1 8 8
1 Black Gold Oil David Gurrola 1 8 8
3 Arrow Board O Ismael Fernandez 1 8 8
Jeremy Wolley 1 8 8
Mario Alvarado 1 10 10
Adam Alvarado 1 9 9
Talno Martines 1 8.5 8.5
Miguel Mivaontes 1 8.5 8.5
Luis Bacona 1 8.5 8.5
Bid
Item Description Quantities Ivan Alverado 1 8.5 8.5
A-2 Traffic Control And
Public Safety 1 Fernando
Adodaca 1 8.5 8.5
B-21 ARHM 2.5 Overlay 1556.26 tons Adam Alvarado 1 9 9
B-19 2.5 Grind Out 2425 LF Martin Perciado 1 8.5 8.5
Elins Sanchez 1 8.5 8.5
Jose Deln Riva 1 9 9
Jose Guence 1 9.5 9.5
Guillemo Macrel 1 8.5 8.5
REPORT NO. 54
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/23/2024
Day of Week: Tuesday
Start Time: 7:00
Finish Time: 5:00
Total Hours: 9.5
DAILY REPORT
Page 3 of 5
(O)- Owner / Operator
(R)- Rental
(F) - Foreman Company COMPANY TRADE
American
Pavement
System (Slurry)
2 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver Traffic Control ID Hrs. EQUIPMENT NAME
1 Lowboy
Loader O Donato
Franco 2 A16 9
1 Slurry Truck O Eduardo De
Santiago 2 A16 9
1 Slurry Truck O Frank Murrillo 2 A16 9
1 Slurry Truck O Luis
Arizmendi 2 A16 9
1 TC Truck O Jose Cordova 2 A16 9
1 TC Truck O Rudy Valdez 2 A16 10
1 TC Truck O George
Sanchez 2 A16 9
1 Pickup O Gilbert
Sanchez 2 A16 9
1 Pickup R Alberto
Medina 2 A16 10
1 Dump
Truck/Roller R Jeff Hunter 2 A16 10
1 Tanker R
Saw Truck R
Bid
Item Description Qtys
A-16 Application of Type ll
slurry seal 170485 square feet
REPORT NO. 54
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/23/2024
Day of Week: Tuesday
Start Time: 7:00
Finish Time: 5:00
Total Hours: 9.5
DAILY REPORT
Page 4 of 5
Photos
Work in progress
REPORT NO. 54
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/23/2024
Day of Week: Tuesday
Start Time: 7:00
Finish Time: 5:00
Total Hours: 9.5
DAILY REPORT
Page 5 of 5
Work in progress
End of Report