HomeMy WebLinkAbout20240722 Daily Report
REPORT NO. 53
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/22/2024
Day of Week: Monday
Start Time: 7:00
Finish Time: 4:15
Total Hours: 8.5
DAILY REPORT
Page 1 of 5
Prime Contractor’s Activities:
• ONYX paving crew laid out 2.5" of A.C on Grande Ave from STA 156+00 to STA
162+00.
• Approximately 600 LF of A.C were placed.
• The contractor used a paving machine to lay down the A.C and two rollers were at
the job site compacting the A.C.
• I met a soil technician at the job site. The technician from GMI was hired by the contractor to conduct
compaction tests on the A.C.
• Black Gold oil truck sprayed oil on all grinded A.C prior to paving
• Black gold sand truck sprayed sand on all new asphalt to minimize tracking.
Materials Placed/Quantities Measured:
• ONYX paving crew placed 1062.31 tons of A.C on Golden Spring Drive using mix design ARHM – GG – C
½” PG 64- 16. Per approved plan.
• American Asphalt South, Inc. Slurry seal crew placed 185,466 square foot of Type 2 slurry seal on various
streets.
•
Sub-Contractors/Sub-Consultants Activities:
• Pavement rehab grinding crew grinded 2.5" of A.C on Grand Avenue using 7’ wide grinder between STA
39+00 and STA 54+00. Approximately 1500 LF were completed.
• A sweeper was at the job site all day cleaning up the job site and a water truck was at the job site spraying
the grinded street to minimize the dust.
• American Asphalt crew laid out Type 2 slurry seal on the following streets.
o Pasado Dr from Ambushers St to Cul De Sac
o Falcon Ridge Dr from Highbluff Rd to Hawkwood Rd
o Fair Wind Ln from Falcon Ridge Rd to Cul De Sac
o Castle Rock Rd from Fountain Springs Hipass Rd
o Hidden Pines Dr from Sunbright Dr to Castle Rock Rd
o Ambushers St from Crooked Creek Dr to Honeybrook Ln
o Woodhull Cir from Ambushers St to Cul-de-sac
o Hipass Dr from Castle Rock Rd to Cul-de-sac
Traffic Control:
• The contractor placed traffic control per approved plan. They placed road construction signs and cones
throughout the project in the vicinity of the construction zone. The contractor provided flagmen throughout
the project as needed.
Visitors:
• Christian Malpica
Notes:
Weather
Cool AM
Hot PM
Temperature
69 Min
93 Max
REPORT NO. 53
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/22/2024
Day of Week: Monday
Start Time: 7:00
Finish Time: 4:15
Total Hours: 8.5
DAILY REPORT
Page 2 of 5
Manpower / Equipment
(O)- Owner / Operator
(R)- Rental
(F) - Foreman
COMPANY TRADE
Onyx
Construction 1 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver ID Hrs. # EQUIPMENT NAME
1 Foreman Truck O Jose Becerra 1 A2 8 8
1 Skip Loader O Nathan
Becerra 1 B19 8 8
1 Sweeper R Arron Becerra 1 B21 8 8
1 TC Truck O Brett Dare 1 8 8
1 Water Truck O Ismael
Fernandez 1 8 8
1 Grinder O Vincet
Fernandez 1 8 8
1 Mini Grinder O Jeremy
Woolley 1 8 8
1 Supper 10 Dump R Mario
Solorzano 1 8 8
20 Loaded Truck O Richard
Alvarez 1 8 8
1 Crack Sand Truck O Moses
Twyman 1 8 8
1 Paving Machine O Edger
Vasguez 1 8 8
3 Roller O Bryan Posas 1 8 8
1 Black Gold Sand Michael
Rincon 1 8 8
1 Black Gold Oil David Gurrola 1 8 8
3 Arrow Board O Ismael
Fernandez 1 8 8
Jeremy
Wolley 1 8 8
Mario
Alvarado 1 10 10
Adam
Alvarado 1 8.5 8.5
Talno
Martines 1 8.5 8.5
Miguel
Mivaontes 1 8.5 8.5
Luis Bacona 1 8 8
Bid
Item Description Quantities Ivan Alverado 1 8 8
A-2
Traffic
Control And
Public Safety
1 Fernando
Adodaca 1 8 8
B-21 ARHM 2.5
Overlay 1062.31 tons Adam
Alvarado 1 8.5 8.5
B-19 2.5 Grind Out Martin
Perciado 1 8 8
Elins Sanchez 1 8.5 8.5
Jose Deln
Riva 1 9 9
REPORT NO. 53
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/22/2024
Day of Week: Monday
Start Time: 7:00
Finish Time: 4:15
Total Hours: 8.5
DAILY REPORT
Page 3 of 5
Jose Guence 1 9 9
Guillemo
Macrel 1 8 8
(O)- Owner / Operator
(R)- Rental
(F) - Foreman Company COMPANY TRADE
American
Pavement
System
(Slurry)
2 Bid Item No. Total Hours Foreman Laborer Operator Mason Apprentice Opry. Engineer Saw Cutter Truck Driver Traffic Control ID Hrs. EQUIPMENT NAME
1 Lowboy
Loader O
Donato
Franco 2 A16 9
1 Slurry
Truck O
Eduardo De
Santiago 2 A17 9
1 Slurry
Truck O
Frank
Murrillo 2 9
1 Slurry
Truck O
Luis
Arizmendi 2 9
1 TC Truck O
Jose
Cordova 2 9
1 TC Truck O Rudy Valdez 2 10
1 TC Truck O
George
Sanchez 2 9
1 Pickup O
Gilbert
Sanchez 2 9
1 Pickup R
Alberto
Medina 2 10
1 Dump
Truck/Roller R Jeff Hunter 2 10
1 Tanker R
Saw Truck R
Bid
Item Description Qtys
A - 2 Traffic control
B-19 Cold mill 2.5"
B-21 ARHM over lay
2.5”
A-16 Application of Type
ll slurry seal
A-17 Application of Cape
seal
B-3 Water pollution
control
REPORT NO. 53
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/22/2024
Day of Week: Monday
Start Time: 7:00
Finish Time: 4:15
Total Hours: 8.5
DAILY REPORT
Page 4 of 5
Photos
REPORT NO. 53
City of Diamond Bar
Project: Area 3 Residential & Collector Streets
Rehabilitation and Arterial Street Rehabilitation Project
Project/Specification No.: SI24101 & SI24103, CIP No.
PW23402
Contractor: Onyx Construction
Project Inspector: Mamoun Aldwir
Date: 7/22/2024
Day of Week: Monday
Start Time: 7:00
Finish Time: 4:15
Total Hours: 8.5
DAILY REPORT
Page 5 of 5
Work in progress
End of Report