HomeMy WebLinkAboutSlurry Seal Project - Area 1.msgGood Morning,
As part of the City’s slurry seal cycle program, below is the information for our scheduled “Residential & Collector Streets Rehabilitation (Area 1) and Arterial Street Improvements
(Golden Springs Road from Brea Canyon Road to Lemon Avenue) project:
Construction Period: June 27, 2022 – August 31, 2022
Project Description
Residential and collector streets (Area 1)
* Slurry seal
* Chip seal
* Localized asphalt concrete
* Curb ramp reconstruction
*
Street rehabilitation on Golden Springs Drive from Brea Canyon Road to Lemon Avenue.
* Pavement grind and overlay between 2” – 4”
* Enhanced bicycle lane striping
* Roadway signing and striping
* Curb ramp reconstruction
See attached project vicinity maps for your information.
Let me know if you have any questions or comments.
Thank you.
Christian Malpica | Associate Engineer
City of Diamond Bar | Public Works Department
909.839.7042
<https://www.diamondbarca.gov/1019/Make-An-Appointment>