HomeMy WebLinkAboutTraffic Control Switch at Grand Avenue & Golden Springs Drive.msgFYI – The contractor has made notable progress on the project, successfully finishing the construction of the precast concrete west tunnel and preparing to commence work on the east
tunnel by next week. In order to facilitate the construction of the precast concrete of the east tunnel, a traffic control and striping change has been scheduled for this Friday night
at 9 PM, redirecting traffic to the northbound lanes on Grand Avenue. The contractor will maintain at least one lane open at all the times during the switch to ensure smooth traffic
flow.
If you have questions, please let me know, or contact:
Jason Fuentes, Public Works Inspector
(City of Diamond Bar)
Cell Phone: 909-208-3943
Thank you.
Christian Malpica | Associate Engineer
City of Diamond Bar | Public Works Department
909.839.7042