From: Richard Fisher <rfisher@rfaland.com>
Sent: Thursday, December 15, 2022 10:17 PM
To: Ryan Wright <RWright@DiamondBarCA.Gov>; Anthony Jordan <AJordan@DiamondBarCA.Gov>
Subject: City-Initiated Change Order No.1
CAUTION: This message originated outside of our City of Diamond Bar network.
**Please exercise caution when opening attachments or clicking links, especially from unknown senders.**
Hi Guys:
I have attached both a Red-texted Plan highlighting the locations and notes for revised work items and their quantities (both projected additional costs and earned credits), and the
DRAFT language for the descriptions of revised construction items directly relating to these highlighted amenities.
With a small exception of MINIMAL construction supervision required for the item A-2, I have taken the awarded Contracts Bid Schedule prices and applied these to both additional quantities
and deleted quantities of work. Hopefully, there is an extremely minimal need to get involved in “Negotiated Costs” dialogue.
I have not determined the precise additional work days involved, but suggest perhaps NMT 10 working days would be warranted.
Let me know what questions you may have.
Best,
Dick Fisher
Richard Fisher Associates
4902 Kron Street, Irvine CA 92604
(714) 342-5467
rfisher@rfaland.com <mailto:rfisher@rfaland.com>