HomeMy WebLinkAboutRFI #11AREQUEST FOR INFORMATION
RFI #3
TO: Mr. Ryan Wright (Via Email) RFI #: 11A
FROM: Danny Daher BID PACK #: FP17500 Prime Contractor
PROJECT NAME: Canyon Loop Trail
Drawing Ref.: Quantity Changes per field conditions. Specification Ref.:
DESCRIPTION OF CLARIFICATION / INFORMATION REQUIRED:
Steps 1 &2 constructed and completed per as directed 3 risers runs and 30” landings for a total length of
90’
Steps 4 -6 to be constructed for a total length of 36' (30' run +6' landing)
Steps 17-26 to be constructed for a total length of 74’ (70' run +4' landing)
Total length of steps when completed will be 200’
Bid item #9 shows estimated quantity of 153’
Wanted to make sure that Bid item #9 is going to change and reflect 200’ as quantity prior to
purchasing more timber.
Please review and comment.
PROPOSED SOLUTION:
SCHEDULE IMPACT (x ) YES ( ) NO COST IMPACT (x ) YES ( ) NO
RESPONSE REQUIRED BY: _01/18/2023_______________________
RFI by: Danny Daher Date: 01/11/2023
Contractor certifies this RFI is required, sketches are attached and RFI is complete.
RESPONSE:
________________________________
__________________________________________________________________________________________
___________________________________________________________________________________________
This document is to provide additional information or clarification only. This is not a request for, nor an authorization or direction to proceed with additional work, nor a time extension of the Contract period.
Response by: Date:
(Architect) (initial)
Title:
Received by: Date: