HomeMy WebLinkAboutConst Schedule 11142022Updated Construction Schedule
Date:11/8/2022Job Name:Canyon Loop Trail Improvements
Job No.FP17500
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15
10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27
Mobilization X
Order Sheds, Benches, Rock, Timber, Baskets, Rebar, Etc.100% Completed except sheds X X
Construction Staking 100% Completed X X X
Clear and Grub; Storm Water Control 100% Completed X X X
Demolition of Post & Rail Fencing 100% Completed X X
Trail Grading / 5' Wide 100% Completed X X X XEarthwork, Excavation for Gabion Walls 99% Completed X X XSpreading Excess Earthwork 99% Completed X X X
Setting Baskets for Gabion Walls Started 11/14 X X X
Transporting Rock to Location of Walls Will Start week 6 or sooner pending delivery X X XFilling Gabion Walls Will Start week 6 or sooner pending delivery X X XBackfill and V Swale Install Will Start week 6 or sooner pending delivery X X X
Velocity Reducer and Water Diverters Will Start week 6 or sooner pending delivery X XTimber Steps Install Will Start week 5 X X X X XShelter Structures and Benches Install Will start week 8 "Benches only"X X X X
Signs Install Will Start week 8 X X X X X
Hydroseeding Will Start week 12 X
WORK ACTIVITY COMMENTS