HomeMy WebLinkAboutConst Schedule 11142022Updated Construction Schedule Date:11/8/2022Job Name:Canyon Loop Trail Improvements Job No.FP17500 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 Mobilization X Order Sheds, Benches, Rock, Timber, Baskets, Rebar, Etc.100% Completed except sheds X X Construction Staking 100% Completed X X X Clear and Grub; Storm Water Control 100% Completed X X X Demolition of Post & Rail Fencing 100% Completed X X Trail Grading / 5' Wide 100% Completed X X X XEarthwork, Excavation for Gabion Walls 99% Completed X X XSpreading Excess Earthwork 99% Completed X X X Setting Baskets for Gabion Walls Started 11/14 X X X Transporting Rock to Location of Walls Will Start week 6 or sooner pending delivery X X XFilling Gabion Walls Will Start week 6 or sooner pending delivery X X XBackfill and V Swale Install Will Start week 6 or sooner pending delivery X X X Velocity Reducer and Water Diverters Will Start week 6 or sooner pending delivery X XTimber Steps Install Will Start week 5 X X X X XShelter Structures and Benches Install Will start week 8 "Benches only"X X X X Signs Install Will Start week 8 X X X X X Hydroseeding Will Start week 12 X WORK ACTIVITY COMMENTS