Completion date Anytime no later than 6/30/2020
Scope of Work
Not Included
Company Proposal
Construction Bid Form
Trees to be removed and re-planted by Diamond Bar Public Works. Diamond Bar Public Works to provide permits needed to install
EV units and begin scope of work.
Owner Information Contractor Information
Project name Diamond Bar City Hall EV install
To install 5 new level-2 UL Certified Noodoe charging stations ( 1 single pedestal
and 2 double pedestals) in the parking lot as designated by the City
of Diamond Bar.
Item A. To run approximately 100 feet conduit from panel ''GLA'' to
the outside of building in designated location next to ATS switch.
Item B. To trench approximately 90 feet to the furthest charging
station and install PVC conduits to feed power to the new charging
stations.
Item C. Fame and poor 3 pedestal pads.
Item D. Run power conductors from panel ''GLA'' to new charging
stations. As well as communications.
Design and engineering to be done prior to the start of the project.
This estimate includes labor, materials.
Owner Acceptance
10/29/2019
Submitted by (home owner or authorized representative) Date
We, Noodoe Ev LLC, propose the above scope of work, to be completed by no later than June,30, 2020 or anytime upon city
approval to start project installation prior to June 2020 for the amount of $45,622.75. Upon approval from Diamond Bar Public
Works and after receiving all permits we will begin install and be complete in 20 calender days.
We, City of Diamond Bar, do accept the above scope of work, proposed to be completed by June 2020 for the amount of
45,622.75.
Samuel Yuan
Submitted by (Company Representative) Date
Page 2 of 6
Qty. Description Cost Total
5 Noodoe S1000/S2000 charger with pedestal $800.00 $4,000.00
1 Conduit $1,500.00 $1,500.00
1 Hardware $1,500.00 $1,500.00
1 Breakers $1,500.00 $1,500.00
1 Wire $1,500.00 $1,500.00
3 concrete footing/foundation 6'' thick $465.00 $1,395.00
106 Building wire specialist $110.00 $11,660.00
1 Engineering and Designs $3,472.95 $3,472.95
112 Journeyman Electrician $136.00 $15,232.00
Subtotal $41,759.95
Tax rate 9.25%
Tax $3,862.80
Grand total $45,622.75
Cost Breakdown
List of Materials and Costs