HomeMy WebLinkAbout20200717111619836March 30, 1979
W.O. 605D
Santa Ana
County of Los Angeles
Department of County Engineering
550 S. Vermont
Los Angeles, California
Attention: Mr. Ray Waldbaum
Subject: Periodic Grading Progress Report, Tracts 29053,
34160 and 34161; for the periods from December
18, 1978 through March 31, 1979; Diamond Bar,
County of Los Angeles, California.
Gentlemen:
The following report summaries grading operations along with
the geologic and soil conditions encountered to date, since
our last in -grading report dated December 22, 1978, for
Tracts 29053, 34160 and 34161, Diamond Bar, County of Los
Angeles, California. Grading progress is presented chrono-
logically in intervals of approximately 15 days. Each in-
terval contains subheadings and commentaries summarizing the
grading and inspections performed during that time.
DECEMBER 18 - 31
Job was shut down due to rain, between December 18 and the
26th.
FILL AREAS
Compacted fill was placed in the vicinity of Lots 85-95, and
in the stabilization fill south of Lot 100 (Tract 34161). w
I
T 1 0 N APR 1979
2)
SUBDRAINAGE
286 feet of backdrains were placed in the stabilization
south of Lot 100 (Tract 34161).
CUT AREAS
Areas which were undergoing mass excavation during this
period included Lots 1-19 and 87-100 (Tract 34161).
Finishing was being performed on lots adjacent to Chirping
Sparrow Road and Running Branch Road.
JANUARY 1 - 31
Due to rain,grading operations were shut down between January
5, 1979 to January 21, 1979 and from January 30, 1979 to
January 31, 1979.
STABILIZATION
A buttress fill south of Lot 100 (Tract 34161) was completed
by overfilling and trimming back the face of the slope.
Excavation of a 15'wide by 3'deep stabilization key for the
slope south of Lot 78 (Tract 29053) was begun.
3)
Tl T TT T C1 T T T TTfl
Finishing of lots along Hawkwood Road and Chirping Sparrow
was being performed during this time for both Tracts 34161
and 29053.
ADDITIONAL WORK
Additional work being performed for Tracts 34161 and 29053
included the cleaning out of the desilting basins and erosion
repairs.
FEBRUARY 1 - 28
Due to rain grading operations were shut down for all but
about 6 days out of the entire month.
STABILIZATIONS
A 15'wide by 3'deep stabilization key was excavated, inspected
and approved to receive fill for the slope south of Lot 78
Tract 29053).
FILL AREAS
Minor amounts of fill were being placed in the vicinity of
Lots 70 and 71 (Tract 29053).
4)
Cut excavation was being performed in the vicinity of Lots
79-82 (Tract 29053).
ADDITIONAL WORK
Additional work included repairs of minor erosion damage to
streets, pads and slopes along Running Branch Road and Chirping
Sparrow Road.
MARCH 1 - 30
FILL
Fill was placed on Lots 80-84 (Tract 29053) and in the stability
fill south of Lot 78 (Tract 29053).
CUT
Minor cuts were made on Lots 78-82 (Tract 29053),and in the
streets.
FINISHING
Finishing of pads, slopes and streets were accomplished on
Lots 79-82 (Tract 29053) and on streets and slopes along
Chirping Sparrow Road, Running Brach Road and Goldrun.
1 (
5)
GEOLOGIC CONDITIONS
With the exception of minor folding and shearing, geologic
conditions including bedrock structure, are generally as
anticipated.
CLOSURE
If there are any questions concerning this letter please
contact our office at your convenience. The findings con-
tained herein are in accordance with generally accepted
professional principles and practice in the fields of soil
mechanics, foundation engineering and engineering geology.
This warranty is in lieu of all other warranties, either
expressed or implied.
Res ally submitt d,
By: ffj'
Ct
FIL14OY7
ACK D. THOMPSO9,C.E_G.68_2_
EDALL, ARAGON, WORSWICK & ASSOCIATES, INC.
C: (2) Addressee
1) Weatherfield Homes Inc. Att: Mr. Gil Wilkson
1) VTN Consolidated.