August 14, 2015 Review of simplified grading for new driveway with Greg
Gubman, Community Development Director. Agreed that new
plan was better than the first one submitted with its series of
retaining walls. No additional Planning review would be
required. Mike Verdugo (Verdugo & Associates: VA) and Ken
Kurose (Ken Kurose Architect: KKA).
September 18, 2015 VA and KKA meet with Jeff Tol, Permit Technician/Building
Inspector and submitted revised plans for plan check. J. Tol said
no additional permit fees would be needed at this time but
would be calculated later. He said there would be quick turn-
around for the review. VA and KKA noted we had met with G.
Gubman earlier in August.
October 8, 2015 KKA called City of DB to inquire about progress of plan check;
was notified they could not answer as J. Tol was on “medical
leave”. Talked with Aaron Lucas.
October 9, 2015 KKA called again and talked both with A. Lucas and Esmeralda
(last name?) to get more clarification on plan check status.
October 15, 2015 KKA called DB and talked with A. Lucas and was informed
structural corrections were past due by 1 week.
October 20, 2015 Upon learning plan check corrections were ready for pick-up, VA
to DB to pick up plans. Only structural plans were reviewed.
October 28, 2015 VA at DB to drop off the plans with the structural corrections.
November 17, 2015 VA was notified by J. Tol via phone call that plans were ready for
pick up; KKA to DB to pick up the plans. New corrections from
Grading and Planning were included for the first time for the
revised driveway plan.
December 8, 2015 VA and KKA to DB to meet with Russell (last name?) for 4:00 PM
review; VA and KKA missed Russell due to traffic. Met with
Raymond Tao, Building Official, who brought in Sterling Mosley,
PROPOSAL FOR ARCHITECTURAL SERVICES
YUAN RESIDENCE
22819 CANYON VIEW ROAD
September 10, 2014
Page 2 of 2
365.City of Diamond Bar.Time Line for Revised Plan Review.12-16-15.doc
Grading, and May Nakajima, Planning. We discussed how we
were not expecting new corrections from Planning per first
discussion with G. Gubman. Discussed grading corrections with
S. Mosley.
December 15, 2015 Received email from M. Nakajima saying the deck over the
driveway entrance and the supporting retaining walls would be